Skip to content
Metal Structures · 6 min ·

Metal Structure Installation: Technology, Stages, and Quality Control

A structure fabricated to drawings still has to be assembled correctly on site — from foundation prep to verifying the plumb of the finished frame.

Site and foundation preparation

Before erection, a survey checks foundation axes and elevations, plus the position of embedded plates and anchor bolts — deviations at this stage carry through the entire frame and are hard to correct once assembly starts. In parallel, structures are delivered to site and laid out by shipping mark per the shipping schedule.

Sub-assembly and lifting

Large members (trusses, frame sections) are often sub-assembled into larger blocks on the ground and then lifted whole by crane — this reduces at-height work and the number of field joints in hard-to-reach spots. The lifting sequence and temporary bracing before permanent connections are set is defined by the erection method statement, not improvised by the crew on site.

Field connections: bolts and welding

The main field connections on site are bolted (including high-strength bolts with controlled tensioning) and welded. Bolted connections are preferred where erection speed matters and no post-weld corrosion touch-up is needed; welded connections where a monolithic joint is required. Requirements for each connection type are set already at the KMD stage — the erection crew does not choose them arbitrarily.

Erection quality control

After each tier or section of the frame goes up, a survey verifies column plumb, beam level, and overall geometry against the design. Field welds are checked visually and, for critical joints, by ultrasonic testing — before the structure is closed in by cladding or enclosure panels.

Safety on work-at-height erection

Erecting frames and pipe racks is work at height with lifting equipment, so the crew needs certification for height and rigging work, and the site needs a cordoned danger zone, fall-arrest systems, and a lift plan coordinated with the crane. This is not a formality — most industrial customers require it before a crew is admitted to site.

Need metal structure installation on site?

UK-ZTO-AN erects fabricated structures with its own crews on site — from foundation to handover of the frame for follow-on work.

All articles

How an Electrostatic Precipitator Works: Design, Operating Principle, Applications

Electrostatic Precipitator Manufacturing in Kazakhstan: What to Check Before Choosing a Supplier

Metal Structures: Types, Materials, and How to Order Fabrication

Bag Filters: Design, Operating Principle, and How to Choose One

Belt Conveyors: Design, Types, and Capacity Calculation

Scraper Conveyors: Design and When to Choose One Over a Belt Conveyor

Screw Feeders: Design, Operating Principle, and Applications

Bucket Elevators: Types, Design, and How to Select One

Screw Crushers: Design, Operating Principle, and Applications

Welding Metal Structures: MIG/MAG, TIG, or Electrode — How to Choose

Cyclone Dust Separators: Design, Operating Principle, and When to Use Them

Powder Coating or Hot-Dip Galvanizing: Choosing Corrosion Protection for Metal Structures

Plasma or Gas Cutting: What is the Difference and Which to Choose

Non-Destructive Testing of Welds: VT, UT, RT, MT, and PT Methods

How to Estimate the Cost of Metal Structures: What Drives the Price

Electrostatic Precipitator Spare Parts: What Fails Most Often

Electrostatic Precipitators for CHP Plants and Boiler Houses: Removing Ash from Flue Gas

Electrostatic Precipitator or Bag Filter: Which to Choose for Gas Cleaning

Electrostatic Precipitators for Cement Plants: Kiln and Cooler Gas Cleaning

Precipitator Upgrades: Modernising Old Equipment Without Full Replacement

Metal Structure Design: KM and KMD Drawings, Loads, Codes

Conveyor and Elevator Repair vs. Modernization: When to Fix, When to Replace

Equipment Installation and Commissioning on Site